10. Process Models: Planning and Iteration#

Level: Practitioner · Reading time: 22 min · Exercise: 45 min Prerequisites: none. Measuring Model Quality helps for the baseline step.

In one sentence: After this chapter you can plan a model-based feature so that the uncertain model work and the predictable engineering work are scheduled separately, with decision points agreed in advance.

Why this matters#

Your manager asks for an estimate. The triage feature needs a model, a pipeline, an interface, and monitoring. You give six weeks, because that is what a feature of this size usually takes.

Week four arrives. The prompt is at 84 percent and nobody knows whether 90 is reachable. The pipeline is built, the interface is designed, and both wait on the model. The team works weekends and ships something nobody has measured against a baseline.

The plan treated research as if it were construction. This chapter is about planning work whose outcome you cannot know in advance.

The core idea#

Two professions with different habits build every ML product. Data scientists work by exploration: try a model, measure it, change something, measure again. Software engineers work by process: gather requirements, design, implement, test, deploy, maintain. Kästner's point is that both are reasonable and that they clash when nobody names the difference (chapter 20).

Software engineering has named its trade-offs. The waterfall model, from Royce's 1970 paper, orders development as requirements, design, implementation, and testing. Even its first version allowed a loop back from design to requirements and a pass through the whole sequence to build a prototype. The spiral model repeats those steps to build increasingly complete prototypes, starting with the riskiest parts. Agile methods work in short sprints, typically two weeks or thirty days, with daily stand-up meetings and replanning after each sprint. All of them trade up-front planning against iteration: aerospace software leans toward waterfall, a social network or a start-up toward agile, and Kästner expects many, though not all, ML products to fall on the agile side (chapter 20).

The difference is what an iteration produces. Kästner contrasts model work with two of these models, line by line (chapter 20):

Iteration in software Iteration in model work
What one loop yields Working functionality An answer: better, worse, or no change
Can it be scheduled? Mostly, for known work The time can be capped. The result cannot be promised.
How progress looks Steady, roughly linear Long flat stretches, then a jump
When you are done The requirement is met When quality is good enough, or time runs out
Why loop back, in the spiral model To prove the riskiest part first Work does not split neatly into risky and safe parts, and nobody can say whether a target accuracy is reachable
Why loop back, in agile work To clarify vague requirements and react to change The goal is usually clear. The open question is whether a model can meet it
Splitting work Design supports divide and conquer, so people work in parallel Model work is hard to decompose into independent pieces
Dead ends Rare, outside highly experimental projects Common: many iterations change nothing

Kästner describes data-science work as a science mindset and notes that it is nearly impossible to say in advance how long building a model will take or what accuracy it will reach (chapter 20).

The analogy is a walk versus a search. Building a known feature is a walk: you know the route and can estimate the time. Finding a model that works is a search: you can decide how long you will look, not what you will find. The analogy breaks on the map: a search through model designs gives partial results along the way, which often turn out to be good enough to ship.

What the practitioners say#

How to plan under uncertainty#

A procedure that respects both mindsets:

1. Write the goal and the minimum useful quality#

State what the feature must achieve and the worst quality you would still ship. Without that number, iteration has no end.

2. Build the measurement before the model#

Collect a labeled set, compute a baseline, and make scoring one command. No measurement, no iteration.

3. Run a time-boxed spike#

Give the simplest approach a fixed short time: a few rules, a small model, or a plain prompt. The spike answers one question: is this problem tractable at all?

4. Split the work into two tracks#

Track Contains How to plan it
Model track Prompts, model choice, training data, tuning Time-boxed experiments with a log of what was tried
System track Pipelines, interface, guardrails, telemetry, operations Like ordinary software: tasks, estimates, reviews, tests

5. Agree on the interface between the tracks#

Fix the model's input, output, latency, and cost limits as a contract. The system track then builds against a stub, a stand-in that returns fixed answers, and the model track can change freely underneath.

6. Set decision points in advance#

At each gate, decide with criteria written before the work started: continue, change approach, narrow the scope, or stop. An example: "If the spike is not above the baseline by Friday, we route these tickets by rules."

Figure 1. A plan in two tracks, joined by an interface contract.

flowchart TD
    G["Goal and minimum useful quality"] --> M["Measurement: labeled set, baseline, one scoring command"]
    M --> S["Time-boxed spike: is the problem tractable"]
    S -->|"promising"| C["Interface contract: input, output, latency, cost"]
    S -->|"not promising"| N["Change approach, narrow the scope, or stop"]
    C --> MT["Model track: time-boxed experiments, result not promised"]
    C --> ST["System track: estimated tasks, reviews, and tests"]
    MT -->|"meets the minimum quality"| X["Exploration becomes reviewed, tested pipeline code"]
    ST --> X
    X --> R["Release"]

The two tracks can run in parallel only because the contract fixes what the model hands over.

7. Decide when exploration becomes engineering#

Name the moment when notebooks turn into reviewed, tested pipeline code. Kästner suggests reviewing every change from the point where a pipeline is bound for production (chapter 17).

Pitfalls#

  1. Estimating model work like feature work. Fix: cap the time, never promise the result.
  2. Improving a model with nothing to measure against. Fix: build the evaluation first.
  3. Iterating with no stopping rule. Fix: a minimum useful quality and a deadline, agreed up front.
  4. Letting one track block the other. Fix: an interface contract and a stub.
  5. Shipping the notebook. Fix: a named gate where exploration becomes pipeline code.
  6. Skipping planning because the work is research. Fix: plan the system track fully and the model track as experiments.
  7. Planning the demo, not the product. Fix: put latency, cost, safety, and monitoring on the plan from the start.

Try it#

Write a one-page plan for one model-based feature.

  1. State the goal and the minimum useful quality.
  2. Describe the baseline and how you will score it.
  3. Define a time-boxed spike with a duration.
  4. List the model track and the system track.
  5. Write the interface contract.
  6. Write two decision points with their criteria.

You are done when every uncertain task has a time box and every predictable task has an estimate, when the two tracks can proceed against a stub, and when each decision point names who decides and on what evidence. Stretch goal: run the spike and record, in five lines, what you learned that you could not have planned.

Key takeaways#

Self-check#

  1. What does one iteration produce in model work, as opposed to software work?
  2. Why can you cap the time of a model task but not promise its outcome?
  3. What must exist before any model iteration is worth doing?
  4. How can the system track proceed while the model is still changing?
  5. When should the criteria for a decision point be written?
Show answers 1. An answer about quality: better, worse, or no change. In software, one iteration yields working functionality. 2. Because whether a better model exists is unknown until it is found. The search can be given a deadline, while its result depends on what the data and the problem allow. 3. A measurement: a labeled set, a baseline, and a way to score a candidate against both. 4. Against a stub that honors the interface contract: fixed inputs, outputs, latency, and cost limits. 5. Before the work starts. Criteria written afterward bend toward whatever result appeared.